List of Completed Projects
# | Country | Client | Client Ref. | Type of work | Work Scope | Executed By | Start Date | End Date |
1. | Charleroi (BE) | CMISS.R.L. |
Renato lanno mauro. ianno@cmis.it |
Project Management | Isolation | Accede BVBA | 10/01/2011 | 15/03/2011 |
2. | Wanze (BE) | ALTRAD B. |
Gianni Alessandro gianni.alessandro@altrad.valliauw.com |
Maintenance | Isolation | Accede BVBA | 18/04/2011 | 30/06/2011 |
3. | Hoboken (BE) | RIVERSTONE | - | Prefabrication | Isolation | Accede BVBA | 01/06/2011 | 29/09/2011 |
4. | Paris(FR) | VICTORBUICK |
Mireille van parys mireille.vanparys@victorbuyck.be |
Steel structure | Welding | Accede BVBA | 27/06/2011 | 23/07/2011 |
5. | Tinen (BE) | FABRICOM | Expansion Project | Piping | Accede BVBA | 01/08/2011 | 30/09/2011 | |
6. | Gent (BE) | VERDON |
Patrick Talerico p.talerico@verdon.be |
Expansion Project | Piping | Accede BVBA | 01/08/2011 | 15/10/2011 |
7. | Liege (BE) | FABRICOM | Shut-down | Piping | Accede BVBA | 08/08/2011 | 03/10/2011 | |
8. | Courcelles (BE) | VERDON |
Patrick Talerico p.talerico@verdon.be |
Prefabrication | Piping | Accede BVBA | 10/10/2011 | 03/12/2011 |
9. | Charleroi (BE) | VERDON |
Patrick Talerico p.talerico@verdon.be |
Shut-down | Piping | Accede BVBA | 14/11/2011 | 23/11/2011 |
10. | Mol (BE) | VERDON |
Patrick Talerico p.talerico@verdon.be |
Prefabrication | Piping | Accede BVBA | 15/12/2011 | 07/11/2012 |
11. | Liege (BE) | VERDON |
Patrick Talerico p.talerico@verdon.be |
Shut-down | Piping | Accede BVBA | 20/12/2011 | 31/12/2011 |
12. | Manage (BE) | ALTRAD B. |
Gianni Alessandro gianni.alessandro@altrad.valliauw.com |
Prefabrication | Isolation | Accede BVBA | 15/01/2012 | 30/12/2012 |
13. | Wavre (BE) | VERDON |
Patrick Talerico p.talerico@verdon.be |
Erection | Piping | Accede BVBA | 08/02/2012 | 31/03/2013 |
14. | Liege (BE) | FABRICOM | Shut-down | Piping | Accede BVBA | 15/04/2012 | 04/08/2012 | |
15. | Habay (BE) | KRYNKELS |
Laurent Peiffer laurent.peiffer@krynkels.be |
Paving | Civil Construction | Accede BVBA | 18/04/1012 | 27/06/2012 |
16. | Wanze (BE) | ALTRAD B. |
Gianni Alessandro gianni.alessandro@altrad.valliauw.com |
Maintenance | Isolation | Accede BVBA | 26/04/2012 | 06/07/2012 |
17. | Antwerpen (BE) | INST. SPRINKER | installatiesprincler@planet.nl | Erection | System Fire Protection | Accede BVBA | 12/05/2012 | 21/12/2012 |
18. | Antwerpen (BE) | NEW TERMSERVICE |
Verlinden Jan jan.verlinden@adlex.be |
Food system | Piping | Accede BVBA | 27/06/2012 | 17/08/2012 |
19. | Feluy (BE) | FABRICOM | Walter Vanbuyten | Erection | Piping | Accede BVBA | 12/09/2012 | 28/02/2013 |
20. | Charleroi (BE) | EUROPESTUBES | Gaëtan Ensabella | Prefabrication / Erection | Piping | Accede BVBA | 05/11/2012 | 18/12/2013 |
21. | Wavre (BE) | CEGELEC |
Sofie Goethuys sofie.goethuys@cegelec.com |
Erection | Piping | Accede BVBA | 20/11/2012 | 30/03/2013 |
22. | Willebroek (BE) | FABRICOM | Walter Vanbuyten | Prefabrication / Erection | Piping | Accede BVBA | 10/02/2013 | 31/08/2013 |
23. | Wavre (BE) | AXIMA GDF SUEZ | Karin Bakkouche | Erection | Structure | Accede BVBA | 04/03/2013 | 19/07/2013 |
24. | Courcelles (BE) | VERDON |
Patrick Talerico p.talerico@verdon.be |
Prefabrication | Piping | Accede BVBA | 15/01/2013 | 18/03/2014 |
25. | Genk (BE) | ASOTEP |
Sergio Petosa sergio@asotep.com |
Prefabrication / Erection | Piping | Accede MEC | 15/02/2013 | 30/09/2013 |
26. | Mol (BE) | AXIMA GDF SUEZ | Karin Bakkouche | Prefabrication | Piping | Accede BVBA | 01/04/2013 | 20/12/2013 |
27. | Wavre (BE) | CEGELEC |
Sergio Petosa sergio@asotep.com |
Prefabrication / Erection | Piping | Accede BVBA | 15/07/2013 | 17/12/2013 |
28. | Mons (BE) | VERDON |
Patrick Talerico p.talerico@verdon.be |
Erection | Piping | Accede BVBA | 20/02/2013 | 28/02/2014 |
29. | Wavre (BE) | AXIMA GDF SUEZ | Walter Vanbuyten | Erection | Piping | Accede BVBA | 01/06/2013 | 30/06/2014 |
30. | Manage/Wanze (BE) | ALTRAD B. |
Gianni Alessandro gianni.alessandro@altrad.valliauw.com |
Prefabrication / Erection | Isolation | Accede BVBA | 18/11/2014 | 05/02/2015 |
31. | Barcelona (VE) | PETROCEDEÑO | Jesús Pérez/G. Quevedo | Prep. for Shut-Down | Equipment Maintenance | Accede MEC | 01/05/2013 | 30/09/2013 |
32. | Barcelona (VE) | PETROCEDEÑO | Jesús Pérez/G. Quevedo | Prep. for Shut-Down | Equipment Maintenance | Accede MEC | 01/06/2014 | 31/01/2015 |
33. | Barcelona (VE) | PETROCEDEÑO | Jesús Pérez/G. Quevedo | Shut-Down | Equipment Maint. De-Coking Sys. | Accede BVBA | 01/06/2014 | 31/01/2015 |
34. | Barcelona (VE) | PETROCEDEÑO | Jesús Pérez/G. Quevedo | Shut-Down | Piping (HMU) | Accede BVBA | 01/06/2014 | 28/02/2015 |
35. | Barcelona (VE) | PETROCEDEÑO | Jesús Pérez/G. Quevedo | Shut-Down | Equipmet Rep. Coke Drums | Accede BVBA | 01/11/2014 | 28/02/2015 |
36. | Liége (BE) | EDEL SA | RudiVan Mechelen | Erection | Piping | Accede BVBA | 04/12/014 | 24/04/2015 |
37. | Izegem (BE) | AXIMA GDF SUEZ | RudiVan Mechelen | Erection | Piping | Accede BVBA | 27/04/2015 | 22/05/2015 |
38. | Barcelona (VE) | PETROPIAR PDVSA | G. Ordonez | Erection | Equipment / Tubular Struct. | Accede BVBA | 01/03/2015 | 31/10/2015 |
39. | Barcelona (VE) | SUPERMETANOL PDVSA | G. Ordonez | Shut-Down | Equipment / Structure | Accede BVBA | 01/07/2015 | 31/08/2015 |
40. | Mol / Antwerpen (BE) | FABRICOM | Walter Vanbuyten | Prefabrication / Erection | Piping | Accede BVBA | 10/08/2015 | 19/12/2015 |
41. | Ro1erdam (NL) | SICES |
Claudia Pietrobelli. c.pietrobelli@sicesgroup.com |
Erection | Piping | Accede MEC | 01/09/2014 | 31/08/2015 |
42. | Zeebrugge (BE) | SICES |
Claudia Pietrobelli. c.pietrobelli@sicesgroup.com |
Erection | Piping | Accede MEC | 01/11/2014 | 31/05/2016 |
43. | Courcelles (BE) | VERDON |
Patrick Talerico p.talerico@verdon.be |
Erection | Piping | Accede BVBA | 08/09/2014 | 11/03/2016 |
44. | Genk (BE) | ASOTEP |
Sergio Petosa sergio@asotep.com |
Erection | Piping | Accede MEC | 04/05/2015 | 19/02/2016 |